California's bullet train hurtling toward multibillion-dollar overrun, federal report warns

Los Angeles Times ^ | January 13, 2017 | By Ralph Vartabedian 

California’s bullet train could cost taxpayers 50% more than estimated — as much as $3.6 billion more. And that’s just for the first 118 miles through the Central Valley, which was supposed to be the easiest part of the route between Los Angeles and San Francisco.
A confidential Federal Railroad Administration risk analysis, obtained by The Times, projects that building bridges, viaducts, trenches and track from Merced to Shafter, just north of Bakersfield, could cost $9.5 billion to $10 billion, compared with the original budget of $6.4 billion.
The federal document outlines far-reaching management problems: significant delays in environmental planning, lags in processing invoices for federal grants and continuing failures to acquire needed property.
The California High-Speed Rail Authority originally anticipated completing the Central Valley track by this year, but the federal risk analysis estimates that that won’t happen until 2024, placing the project seven years behind schedule.
The report, the most critical official assessment of the project to surface so far, is labeled a “confidential-draft deliberative document for internal use only” and was presented by senior Federal Railroad Administration executives to California rail authority board Chairman Dan Richard and Chief Executive Jeff Morales on Dec. 1 in Washington. . .
(Excerpt) Read more at latimes.com ...